Match the Agile Process models with the task performed during the model :

List IList II
a. Scrum i. CRC cards
b. Adaptive software development ii. Sprint backlog
c. Extreme programming iii. <action> the <result>
<by/for/of/to> a(n) <object>
d. Feature-driven developmentiv. Time box release plan

Choose the correct option from those given below :
  1. 1. (a)-(ii), (b)-(iv), (c)-(i), (d)-(iii)
  2. 2. (a)-(i), (b)-(iii), (c)-(ii), (d)-(iv)
  3. 3. (a)-(ii), (b)-(i), (c)-(iv), (d)-(iii)
  4. 4. (a)-(i), (b)-(iv), (c)-(ii), (d)-(iii)
Answer : 1. (a)-(ii), (b)-(iv), (c)-(i), (d)-(iii)

Explanation Question 134
  • Scrum → Sprint backlog
  • Adaptive software development → Time box release plan
  • Extreme programming → CRC cards
  • Feature-driven development → <action> the <result> <by/for/of/to> a(n) <object>
So, option 1 is correct answer

PreviousNext
UGC NET CS December 2019 - Question 133UGC NET CS December 2019 - Question 135

No comments:

Post a Comment

UGC NET Computer Science December 2019 | Question 16

Question 16 In a certain coding language. 'AEIOU' is written as 'TNHDZ'. Using the same coding language. 'BFJPV' wil...

Popular Posts