UGC NET CS 2018 July - II Question 59

Question 59
59. Consider the following three processes with the arrival time and CPU burst time given in milliseconds :

Process Arrival Time Burst Time
P1 0 7
P2 1 4
P3 2 8

The Gantt Chart for preemptive SJF scheduling algorithm is _________.

Options:
  1. (1)
  2. (2)
  3. (3)
  4. (4)
Answer : (2)

Explanation Question 59

Question asks for Gantt Chart for preemptive SJF

Option (1) is Not preemptive.

P1 continues execution without being preempted when sorter process P2 with Burst time 4 comes.

Option (2) is Preemptive SJF.
Here, P1 executes for 1 second and then preempted by P2 which executes for 4 seconds. Then P1 finishes its remaining execution  followed by execution of P3.

Option (3) is Not preemptive.
Not pre-emptive as P1 continues execution without being preempted when sorter process P2 with Burst time 4 comes. Each of the processes carries on execution without being preempted.

Option (4) is Preemptive but P2 starts execution even before it's arrival time 1.

So, Option (2) is correct answer. 