Question 134
Match the Agile Process models with the task performed during the model :
Choose the correct option from those given below :
Answer : 1. (a)-(ii), (b)-(iv), (c)-(i), (d)-(iii) | List I | List II |
| a. Scrum | i. CRC cards |
| b. Adaptive software development | ii. Sprint backlog |
| c. Extreme programming | iii. <action> the <result> <by/for/of/to> a(n) <object> |
| d. Feature-driven development | iv. Time box release plan |
Choose the correct option from those given below :
| Previous | Next |
| UGC NET CS December 2019 - Question 133 | UGC NET CS December 2019 - Question 135 |
-
Scrum → Sprint backlog
-
Adaptive software development → Time box release plan
-
Extreme programming → CRC cards
-
Feature-driven development → <action> the <result> <by/for/of/to> a(n) <object>
So, option 1 is correct answer