UGC NET Computer Science December 2019 | Question 84

Question 84
An ______ chart is a project schedule representation that presents project plan as a directed graph. The critical path is the ______ sequence of ______ tasks and it defines project ______ .
  1. 1. Activity, Shortest, Independent, Cost
  2. 2. Activity, Longest, Dependent, Duration
  3. 3. Activity, Longest, Independent, Duration
  4. 4. Activity, Shortest, Dependent, Duration
Answer : 2. Activity, Longest, Dependent, Duration

Explanation
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish

So, option 2 is correct answer

PreviousNext
UGC NET CS December 2019 - Question 83UGC NET CS December 2019 - Question 85

No comments:

Post a Comment

UGC NET Computer Science December 2019 | Question 16

Question 16 In a certain coding language. 'AEIOU' is written as 'TNHDZ'. Using the same coding language. 'BFJPV' wil...

Popular Posts